Central Park Commons

kristakoch

Formerly the location of Lockheed Martin, this 50 acre site is now home to many retail stores and restaurants. Enebak Construction Company’s role was site prep and underground utilities. Enebak worked with the engineer and developer to stay on top of plan changes. As potential tenants changed so did the design.

Major Work:

  • Site Grading: 460,000 Cubic Yards of Excavation
  • Underground Utilities: Sanitary Sewer, Water main, and Storm Sewer
  • Asphalt Removal
  • Underground Pipe Removal
  • Retaining Wall Excavation & Backfill
  • Curb & Sidewalk Removal
  • Contract Amount: $3 Million

Enebak Construction began work in May, 2015 and was completed Fall 2015